Hub Update – February

The builders took a break over the Xmas New Year and they returned to work on Monday the 17th of January

The installation of wiring and air ducting is continuing in the Museum, Visitor Information Centre and the Auditorium.

All these services must be installed before the walls and ceilings can be plastered.

We manage to do a walk through from the entrance of the HUB through the Visitor Information Centre, the Museum, and then through the Library to see what has been happening.